Electric utilities (Federal Power Act):
Hydroelectric licensing regulations,
...of the studies, the applicant files a preliminary licensing proposal, which is subject to comment and additional information requests. 18 CFR 5.16. At least 2 years before the existing license expires, the application must be filed with FERC. 18 CFR 5.17(a). Within 14 days of that filing, F......
-
Electric utilities (Federal Power Act):
Hydroelectric licensing regulations,
...evolve directly into a new Exhibit E that has the form and contents of an applicant-prepared draft NEPA document.\58\ \58\ See proposed 18 CFR 5.16(b). Applicants using the traditional process would continue to use the existing Exhibit E in their license application, and applicants using th......
-
Part II
...of the studies, the applicant files a preliminary licensing proposal, which is subject to comment and additional information requests. 18 CFR 5.16. At least 2 years before the existing license expires, the application must be filed with FERC. 18 CFR 5.17(a). Within 14 days of that filing, F......
-
Separate Parts In This Issue
Part II
Energy Department, Federal Energy Regulatory Commission,
...evolve directly into a new Exhibit E that has the form and contents of an applicant-prepared draft NEPA document.\58\ \58\ See proposed 18 CFR 5.16(b). Applicants using the traditional process would continue to use the existing Exhibit E in their license application, and applicants using th......