40 CFR 60.23 - Adoption and submittal of State plans; public hearings

Cite as40 CFR 60.23
    • This document is available in original version only for vLex customers

      View this document and try vLex for 7 days
    • TRY VLEX
114 practice notes
7 cases
  • Wyoming v. U.S. Dep't of the Interior, Case No. 2:16-CV-0285-SWS (Lead Case)
    • United States
    • United States District Courts. 10th Circuit. District of Wyoming
    • October 8, 2020
    ...In addition, States must notify the public and hold one or more hearings within the State prior to the adoption of any plan. 40 C.F.R. § 60.23(c), (d).Important to the discussion here is the CAA requirement that EPA consider the costs of regulating existing sources independently of the cost......
  • California v. U.S. E.P.A., Case No. 18-cv-03237-HSG
    • United States
    • United States District Courts. 9th Circuit. United States District Courts. 9th Circuit. Northern District of California
    • December 21, 2018
    ...pertained was required to "adopt and submit to the Administrator ... a plan" to implement the guideline "[w]ithin nine months." 40 C.F.R. § 60.23(a)(1). The agency then was required to "approve or disapprove" such implementation plans "within four months after the date required for submissi......
  • California v. U.S. Envtl. Prot. Agency, No. 19-17480
    • United States
    • United States Courts of Appeals. United States Court of Appeals (9th Circuit)
    • October 22, 2020
    ...Under these regulations, states were given nine months to submit an implementation plan after EPA publishes new emissions guidelines. 40 C.F.R. § 60.23(a)(1). Within four months of that deadline, EPA had to approve or disapprove of the plan. Id . § 60.27(b). If a state failed to submit a pl......
  • State v. U.S. Envtl. Prot. Agency, Case No.18-cv-03237-HSG
    • United States
    • United States District Courts. 9th Circuit. United States District Courts. 9th Circuit. Northern District of California
    • May 6, 2019
    ...pertained was required to "adopt and submit to the Administrator ... a plan" to implement the guideline "[w]ithin nine months." 40 C.F.R. § 60.23(a). The agency then was required to "approve or disapprove" such implementation plans "within four months after the date required for submission ......
  • Request a trial to view additional results