TITLE 40 - PROTECTION OF ENVIRONMENT
CHAPTER I - ENVIRONMENTAL PROTECTION AGENCY
PART 63 - NATIONAL EMISSION STANDARDS FOR HAZARDOUS AIR POLLUTANTS FOR SOURCE CATEGORIES
subpart jjjjj - NATIONAL EMISSION STANDARDS FOR HAZARDOUS AIR POLLUTANTS FOR BRICK AND STRUCTURAL CLAY PRODUCTS MANUFACTURING
Table 2 to Subpart JJJJJ of Part 63 - Operating Limits
As stated in 63.8405, you must meet each operating limit in the following table that applies to you.
------------------------------------------------------------------------ For each . . . You must . . .
------------------------------------------------------------------------ 1. Kiln equipped with a DLA........ a. Maintain the average pressure drop across the DLA for each 3- hour block period at or above the average pressure drop established during the performance test; and b. Maintain an adequate amount of limestone in the limestone hopper, storage bin (located at the top of the DLA), and DLA at all times; maintain the limestone feeder setting at or above the level established during the performance test; and c. Use the same grade of limestone from the same source as was used during the performance test; maintain records of the source and grade of limestone; and d. Maintain no VE from the DLA stack.
2. Kiln equipped with a DIFF or DLS/ a. If you use a bag leak detection FF. system, initiate corrective action within 1 hour of a bag leak detection system alarm and complete corrective actions in accordance with your OM&M plan; operate and maintain the fabric filter such that the alarm is not engaged for more than 5 percent of the total operating time in a 6-month block reporting period; or maintain no VE from the DIFF or DLS/FF stack; and b. Maintain free-flowing lime in the feed hopper or silo and to the APCD at all times for continuous injection systems; maintain the feeder setting at or above the level established during the performance test for continuous injection systems.
3. Kiln equipped with a WS......... a. Maintain the average scrubber pressure drop for each 3-hour block period at or above the average pressure drop established during the performance test; and b. Maintain the average scrubber liquid pH for each 3-hour block period at or above the average scrubber liquid pH established during the performance test; and c. Maintain the average scrubber liquid flow rate for each 3-hour block period at or above the average scrubber liquid flow rate established during the performance test; and d. If chemicals are added to the scrubber water, maintain the average scrubber chemical feed rate for each 3-hour block period at or above the average scrubber chemical feed rate established during the performance test.
------------------------------------------------------------------------