Text
Title 43: Public Lands: Interior
Subtitle B: Regulations Relating to Public Lands (Continued)
CHAPTER II: BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR
SUBCHAPTER C: MINERALS MANAGEMENT (3000)
PART 3200: GEOTHERMAL RESOURCE LEASING
Subpart 3271: Utilization Operations: Getting a Permit
3271.13 - How do I obtain approval to build pipelines and facilities connecting the well field to utilization facilities not located on Federal lands leased for geothermal resources
Before constructing pipelines and well field facilities on Federal lands leased for geothermal resources, you as lessee, unit operator, or facility operator must submit to BLM a utilization plan and facility construction permit addressing any pipelines or facilities. Do not start construction of your pipelines or facilities until BLM approves your facility construction permit.