49 CFR 633.27 - Implementation of a project management plan.

Code of Federal Regulations - Title 49: Transportation

Linked as:

Text


Title 49: Transportation

Subtitle B: Other Regulations Relating to Transportation (Continued)

CHAPTER VI: FEDERAL TRANSIT ADMINISTRATION, DEPARTMENT OF TRANSPORTATION

PART 633: PROJECT MANAGEMENT OVERSIGHT

Subpart C: Project Management Plans

633.27 - Implementation of a project management plan.

(a) Upon approval of a project management plan by the Administrator the recipient shall begin implementing the plan.

(b) If a recipient must modify an approved project management plan, the recipient shall submit the proposed changes to the Administrator along with an explanation of the need for the changes.

(c) A recipient shall submit periodic updates of the project management plan to the Administrator. Such updates shall include, but not be limited to:

(1) Project budget;

(2) Project schedule;

(3) Financing, both capital and operating;

(4) Ridership estimates, including operating plan; and

(5) Where applicable, the status of local efforts to enhance ridership when estimates are contingent, in part, upon the success of such efforts.

(d) A recipient shall submit current data on a major capital project's budget and schedule to the Administrator on a monthly basis.

Sponsored links




ver las páginas en versión mobile | web

ver las páginas en versión mobile | web

© Copyright 2012, vLex. All Rights Reserved.

Contents in vLex United States

Explore vLex

For Professionals

For Partners

Company