18 CFR 32.2 - Required exhibits.

Text


Title 18: Conservation of Power and Water Resources

CHAPTER I: FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY

SUBCHAPTER B: REGULATIONS UNDER THE FEDERAL POWER ACT

PART 32: INTERCONNECTION OF FACILITIES

: Application for An Order Directing the Establishment of Physical Connection of Facilities

32.2 - Required exhibits.There shall be filed with the application and as a part thereof the following exhibits:

Exhibit A. Statement of the estimated capital cost of all facilities required to establish the connection, and the estimated annual cost of operating such facilities.

Exhibit B. A general or key map on a scale not greater than 20 miles to the inch showing, in separate colors, the territory served by each utility, and the location of the facilities used for the generation and transmission of electric energy, indicating on said map the points between which connection may be established most economically.

Sponsored links




ver las páginas en versión mobile | web

ver las páginas en versión mobile | web

© Copyright 2012, vLex. All Rights Reserved.

Contents in vLex United States

Explore vLex

For Professionals

For Partners

Company