TITLE 44 - EMERGENCY MANAGEMENT AND ASSISTANCE

CHAPTER I - FEDERAL EMERGENCY MANAGEMENT AGENCY, DEPARTMENT OF HOMELAND SECURITY

SUBCHAPTER D - DISASTER ASSISTANCE

PART 206 - FEDERAL DISASTER ASSISTANCE FOR DISASTERS DECLARED ON OR AFTER NOVEMBER 23, 1988

subpart h - PUBLIC ASSISTANCE ELIGIBILITY

206.228 - Allowable costs.

General policies for determining allowable costs are established in 44 CFR 13.22. Exceptions to those policies as allowed in 44 CFR 13.4 and 13.6 are explained below.

  (a) Eligible direct costs(1) Applicant-owned equipment. Reimbursement for ownership and operation costs of applicant-owned equipment used to perform eligible work shall be provided in accordance with the following guidelines: (i) Rates established under State guidelines. In those cases where an applicant uses reasonable rates which have been established or approved under State guidelines, in its normal daily operations, reimbursement for applicant-owned equipment which has an hourly rate of $75 or less shall be based on such rates. Reimbursement for equipment which has an hourly rate in excess of $75 shall be determined on a case by case basis by FEMA.

  (ii) Rates established under local guidelines. Where local guidelines are used to establish equipment rates, reimbursement will be based on those rates or rates in a Schedule of Equipment Rates published by FEMA, whichever is lower. If an applicant certifies that its locally established rates do not reflect actual costs, reimbursement may be based on the FEMA Schedule of Equipment Rates, but the applicant will be expected to provide documentation if requested. If an applicant wishes to claim an equipment rate which exceeds the FEMA Schedule, it must document the basis for that rate and obtain FEMA approval of an alternate rate.

  (iii) No established rates. The FEMA Schedule of Equipment Rates will be the basis for reimbursement in all cases where an applicant does not have established equipment rates.

  (2) Statutory Administrative Costs(i) Grantee. Under section 406(f)(2) of the Stafford Act, we will pay you, the State, an allowance to cover the extraordinary costs that you incur to formulate Project Worksheets for small and large projects, to validate small projects, to prepare final inspection reports, project applications, final audits, and to make related field inspections by State employees. Eligible costs include overtime pay and per diem and travel expenses, but do not include regular time for your State employees. The allowance to the State will be based on the following percentages of the total amount of Federal assistance that we provide for all subgrantees in the State under sections 403, 406, 407, 502, and 503 of the Act: (A) For the first $100,000 of total assistance provided (Federal share), three percent of such assistance.

  (B) For the next $900,000, two percent of such assistance.

  (C) For the next $4,000,000, one percent of such assistance.

  (D) For assistance over $5,000,000, one-half percent of such assistance.

  (ii) Subgrantee. Pursuant to section 406(f)(1) of the Stafford Act, necessary costs of requesting, obtaining, and administering Federal disaster assistance subgrants will be covered by an allowance which is based on the following percentages of net eligible costs under sections 403, 406, 407, 502, and 503 of the Act, for an individual applicant (applicants in this context include State agencies): (A) For the first $100,000 of net eligible costs, three percent of such costs; (B) For the next $900,000, two percent of such costs; (C) For the next $4,000,000, one percent of such costs; (D) For those costs over $5,000,000, one-half percent of such costs.

  (3) State Management Administrative Costs.

  (i) Grantee. Except for the items listed in paragraph (a)(2)(i) of this section, other administrative costs shall be paid in accordance with 44 CFR 13.22.

  (ii) Subgrantee. No other administrative costs of a subgrantee are eligible because the percentage allowance in paragraph (a)(2)(ii) of this section covers necessary costs of requesting, obtaining and administering Federal assistance.

  (4) Force Account Labor Costs. The straight- or regular-time salaries and benefits of a subgrantee's permanently employed personnel are not eligible in calculating the cost of eligible work under sections 403 and 407 of the Stafford Act, 42 U.S.C. 5170b and 5173. For the performance of eligible permanent restoration under section 406 of the Act, 42 U.S.C. 5172, straight-time salaries and benefits of a subgrantee's permanently employed personnel are eligible.

  (b) Eligible indirect costs(1) Grantee. Indirect costs of administering the disaster program are eligible in accordance with the provisions of 44 CFR part 13 and OMB Circular A87.

  (2) Subgrantee. No indirect costs of a subgrantee are separately eligible because the percentage allowance in paragraph (a)(2)(ii) of this section covers necessary costs of requesting, obtaining and administering Federal assistance.

[55 FR 2307, Jan. 23, 1990, as amended at 58 FR 47996, Sept. 14, 1993; 63 FR 64426, Nov. 20, 1998; 64 FR 55161, Oct. 12, 1999]

Sponsored Ads:




Activate your free trial now

Make your order

Need help? Contact us

Try vLex for FREE for 3 days

Access legal information from United States including:

  • Constitutions
  • Forms and Contracts
  • Legal Books and Journals
  • Case Law
  • News and Business
  • Regulations
  • U.S. Code

Try vLex without any commitment for 3 days and see why you need it.

3

days of Free Access