Title 18: Conservation of Power and Water Resources
CHAPTER XIII: TENNESSEE VALLEY AUTHORITY
PART 1308: CONTRACT DISPUTES
Subpart B: Contracting Officers
1308.14 - Request for relief by TVA.
When TVA believes it is due relief under a contract, the Contracting Officer shall make a request for relief against the Contractor, and shall attempt to resolve the request by agreement. If agreement cannot be reached within a reasonable time, the Contracting Officer shall issue a decision which complies with the requirements of ? 1308.12(b).