TITLE 18 - CONSERVATION OF POWER AND WATER RESOURCES

CHAPTER I - FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY

SUBCHAPTER B - REGULATIONS UNDER THE FEDERAL POWER ACT

PART 12 - SAFETY OF WATER POWER PROJECTS AND PROJECT WORKS

subpart d - INSPECTION BY INDEPENDENT CONSULTANT

12.34 - Approval of independent consultant.

At least 60 days before the initiation of an inspection under this subpart, the licensee must submit to the Director of the Office of Energy Projects Licensing for approval, with a copy to the Regional Engineer, a detailed resume that (a) describes the experience of the independent consultant; and, (b) shows that the consultant is an independent consultant as defined in 12.31(a).

[Order 122, 46 FR 9036, Jan. 28, 1981, as amended at 49 FR 29370, July 20, 1984]

Sponsored Ads:




Activate your free trial now

Make your order

Need help? Contact us

Try vLex for FREE for 3 days

Access legal information from United States including:

  • Constitutions
  • Forms and Contracts
  • Legal Books and Journals
  • Case Law
  • News and Business
  • Regulations
  • U.S. Code

Try vLex without any commitment for 3 days and see why you need it.

3

days of Free Access