TITLE 18 - CONSERVATION OF POWER AND WATER RESOURCES
CHAPTER I - FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY
SUBCHAPTER B - REGULATIONS UNDER THE FEDERAL POWER ACT
PART 12 - SAFETY OF WATER POWER PROJECTS AND PROJECT WORKS
subpart d - INSPECTION BY INDEPENDENT CONSULTANT
12.34 - Approval of independent consultant.
At least 60 days before the initiation of an inspection under this subpart, the licensee must submit to the Director of the Office of Energy Projects Licensing for approval, with a copy to the Regional Engineer, a detailed resume that (a) describes the experience of the independent consultant; and, (b) shows that the consultant is an independent consultant as defined in 12.31(a).
[Order 122, 46 FR 9036, Jan. 28, 1981, as amended at 49 FR 29370, July 20, 1984]